Within this existing strip
shopping center, traditional Semolina dining, kitchen
and bar facilities were created. The existing 3,750
square foot concrete slab in this space was removed
in order to install extensive plumbing and electrical
utilities to service new kitchen & bar equipment
and toilet rooms placed on top of a fresh concrete
slab. A large amount of detailed millwork was installed,
along with a new HVAC system, finish paint and ceramic
tile floors. Work began in August of 2003 and was completed
in October of 2003.